News

MVP Statement :: Nationwide 12 Permit Vacated

Mountain Valley Pipeline is disappointed with the decision by the U.S. Fourth Circuit Court of Appeals to vacate the Clean Water Act Section 404 stream and wetland crossing permit (Nationwide 12 permit) issued by the Huntington District of the U.S. Army Corps of Engineers (USACE). This decision affects stream and wetland crossings along approximately 160 miles of the route in West Virginia, and the MVP team is evaluating options to understand its ability to continue with construction activities that do not include stream and wetland crossings along this portion of the route.

Read the full statement and background information here.
MVP Weekly Reports
Approved VA DEQ Documents
Spread G Inspection Reports
Spread H Inspection Reports
Draft VA DEQ Documents

Info

Variance Request Nos. A-23, A-24, and A-25 - 10/18/18
Request to Modify Stop Work Order - 10/15/18
Variance Request No. A-22 - 10/15/18
Notice of Agency Action - 10/9/18
Variance Request No. MVP-008 - 10/2/18
Variance Request No. D-15 - 9/27/18
Variance Request No. D-17 - 9/26/18
Variance Request No. MVP-007 - 9/25/18
Variance Request No. C-10 - 9/24/18
Variance Request Nos. H-9 and MVP-006 - 9/21/18
Variance Request Nos. D-11 and D-9 - 9/20/18
Variance Request No. F-11 - 9/20/18
Variance Requests Nos. MVP-004 and D-14 - 9/19/18
Variance Request No. B-6 - 9/18/18
Variance Request No. C-5 - 9/7/18
Request for Notice to Proceed No. 27 - 9/5/18
Notification of Court Action - 8/29/18
Variance Request No. A-15 - 8/28/18
Variance Request Nos A-13 and B-7 - 8/17/18
Variance Requests Nos. A-12, I-11, and Update to Variance A-9 - 8/16/18
FERC - Partial Approval of Temporary Stabilization Plan - 8/10/18
Temporary Stabilization Plan - 8/8/18
Updated on Construction within the JNF - 8/2/18
Update to Variance Request No. A-9 - 7/26/18
Variance Request Nos. A-9 and B-5 - 7/23/18
Confirmation of Notification - WVDEP - 7/19/18
30-Day Advance Notification - Auxiliary Facilities - 7/16/18
Variance Request D-9 and D-10 - 7/16/18
Confirmation of Notification - VA DEQ - 7/11/18
Variance Request No. I-8 - 7/11/18
Updated Variance Request No. MVP-003 - 7/10/18
Updated Request for Permission Regarding Cultural Resources - 7/5/18
Notice of Reinstated Nationwide Permit 12 - 7/3/18
Request for Notice to Proceed No. 26 - 7/2/18
Request to Extend Variance No. Bradshaw-1 - 6/29/18
Variance Request No. H-4 - 6/20/18
Variance Request No. A-10 - 6/15/18
Supplemental Materials - 6/14/18
Request for Notice to Proceed No. 25 - 6/13/18
Variance Request No. D-8 - 6/13/18
Variance Requests Nos. B-4, C-4, G-5, and I-7 - 6/12/18
Variance Request Nos. D-5, MVP-003, and C-3 - 6/7/18
Variance Request E-4 - 5/30/18
Variance Request D-7 - 5/30/18
Supplemental Materials - 5/30/18
Variance Request Nos. B-3, F-6, and G-3 - 5/29/18
Variance Request H-6 - 5/29/18
Variance Request D-6 - 5/29/18
Variance Request No. H-5 - 5/25/18
Variance Request E-5 - 5/24/18
Supplemental Materials - 5/24/18 Filing
Variance Request No. E-3 - 5/24/18
Variance Request No. H-2 - 5/22/18
Variance Request No. F-3, I-2, and I-4 - 5/22/18
Variance Requests No. A-5, E-2, and H-3 - 5/18/18
Notice Regarding Project Shipper Commitments - 5/18/18
MVP Request for Notice to Proceed No. 23 - 5/18/18
Variance Request No. D-2
Variance Request No. F-2 - 5/11/18 Filing
Supplemental Materials - 5/11/18 Filing
Update to Variance Request No. D-1 - 5/8/18 Filing
Variance Request No. A-6 - 5-8-18 Filing
Request for Notice to Proceed No. 23
Request for Permission Regarding Cultural Resources
Variance Request No. D-1
Supplemental Materials - 5/3/18 Filing
MVP Request for Notice to Proceed No. 22 - 5/3/18
Update to Variance Request No. Bradshaw-1
Supplemental Materials - Filed 4/25/18
Request for Notice to Proceed No. 21 - 4/24/18
Variance Request No. I-1 - 4/20/18
Updated to Variance Request No. E-1 - 4/17/18 Filing
Variance Request Nos. A-3 and E-1 - 4/13/18/ Filing
Status of Tree-Felling Activities - 4/12/18 Filing
Request for Notice to Proceed No. 20 - 4/6/18
Variance Request No Harris-2 - 4/5/18
Supplemental Materials - 4/5/18 Filing
Variance Request No Bradshaw-3
Clarification to Variance Request No F-1
MVP Request for Notice to Proceed No. 19 - 3-28-18
MVP Request for Notice to Proceed No. 18 - 3/28/18
Supplemental Materials - 3/28/18 Filing
Variance Request Nos F-1 and G-2
Variance Request No MVP-1
Supplemental Materials - 3/26/18 Filing
Public Variance G-1 Revision - 3/22/18
Supplemental Materials - 3/21/18 Filing
Request for Notice to Proceed No 17 - 3/20/18
Request for Notice to Proceed No 16 - 3/20/18
Supplemental Materials - 3/20/18 Filing
Variance Request C-1 - 3/19/18
Supplemental Materials - 3/15/18
Supplemental Materials - 3/14/18 Filing
Request for Notice to Proceed No 15 - Additional Information - 3/14/18
Request for Notice to Proceed No 15 - 3/13/18
Supplemental Materials - 3/9/18 Filing
Request to Notice to Proceed No 14 - 3/5/18
MVP Notice of Route Reversion - 3/1/18
Supplemental Materials - 2/28/18 Filing
Request for Notice to Proceed No 13 - 2/28/18
Request for Notice to Proceed No 12 - 2/28/18
Request for Notice to Proceed No 11 - 2/20/18
Supplemental Materials - 2/14/18 Filing
Supplemental Materials - 2/13/18 Filing
MVP Notice of Commencement - 2/12/18
Request for Notice to Proceed No 10 - 2/12/18
Request for Notice to Proceed No 9 2-7-18
Request for Notice to Proceed - 2/5/18
Supplemental Materials - 2/2/18 Filing
Request for Notice to Proceed No 7 - 2/2/18
Request for Notice to Proceed No 6 - 1/31/18
Supplemental Materials - 1/31/18 Filing
Request for Notice to Proceed No 5 - 1/26/18
Request for Notice to Proceed No 4 - 1/26/18
Supplemental Materials - 1/26/18 Filing
Request for Notice to Proceed No 3 - 1/17/18
Request for Notice to Proceed No 2 - 1/16/18
Request for NTP No 1 - Supplemental Materials - 1/11/18
Request for Notice to Proceed No 1 - 1/15/18
Implementation Plan Supplement - 12/20/17 Filing
Supplemental Materials - 12/20/17 Filing
MVP Answer to Rehearing Requests - 12/12/17
Supplemental Materials - Plan of Development - 12/11/17
Final Plan of Development – 12/5/17
Final Plan of Development - 10/31/17
MVP Certificate Acceptance
Supplemental Materials - 11/9/17
Supplemental Materials – 9/28/17 Filing
Supplemental Materials - 7/27/17 Filing
Supplemental Materials - 7/20/17 Filing
Supplemental Materials – 7/17/17 Filing
Supplemental Materials - 4/18/17 Filing
MVP Response to 3/20 FERC Data Request
MVP Response to 1/27 FERC Data Request
MVP Answer to DEIS Comments - Filed 2/3/17
MVP Response to 1/17 to OEMR Data Request
MVP Response to 12/21 FERC Data Request
MVP Response to 11/15 USFS Information Request
10/19/16 FERC Data Request
October 2016 Proposed Route - 10/13/16 Filing
MVP Response to 3/31 FERC Data Request
FERC Data Request Response