MVP is being recognized as a critical infrastructure project that is essential for our nation’s energy security, energy reliability, and ability to effectively transition to a lower-carbon future. With total project work roughly 94 percent complete, Mountain Valley remains committed to working diligently with federal and state regulators to secure the necessary permits to safely and responsibly finish construction, and we remain committed to bringing it into service in the second half of 2023. 

Capacity for MVP remains fully subscribed under long-term, binding contracts, and the project is strongly supported by a broad coalition of elected federal, state and local officials; state chambers of commerce and other business groups; landowners; public utilities; natural gas producers; and other non-governmental organizations. Increased use of natural gas has played an important role in our country’s efforts to lower carbon emissions and keep energy prices affordable. 

More than 300,000 miles of interstate and intrastate natural gas transmission pipelines operate every day across the U.S., safely and reliably transporting natural gas for use in homes and businesses to power modern life. None of these existing pipelines have undergone the extensive level of environmental research, analysis and review that has been performed on the MVP project, and we appreciate the strong support and ongoing efforts of so many men and women who, for the past seven years, have continued to work diligently to complete this important project.

The Mountain Valley Pipeline (MVP) project is a natural gas pipeline system that spans approximately 303 miles from northwestern West Virginia to southern Virginia – and as an interstate pipeline will be regulated by the Federal Energy Regulatory Commission (FERC). The MVP will be constructed and owned by Mountain Valley Pipeline, LLC (Mountain Valley), which is a joint venture of EQM Midstream Partners, LP; NextEra Capital Holdings, Inc.; Con Edison Transmission, Inc.; WGL Midstream; and RGC Midstream, LLC. EQM Midstream Partners will operate the pipeline and own a significant interest in the joint venture.

With a vast supply of natural gas from Marcellus and Utica shale production, the Mountain Valley Pipeline is expected to provide up to two million dekatherms per day of firm transmission capacity to markets in the Mid- and South Atlantic regions of the United States. The MVP will extend the Equitrans transmission system in Wetzel County, West Virginia, to Transcontinental Gas Pipeline Company’s (Transco) Zone 5 compressor station 165 in Pittsylvania County, Virginia. As currently planned, the pipeline will be 42 inches in diameter and will require approximately 50 feet of permanent easement (with 125 feet of temporary easement during construction). In addition, the project will require three compressor stations, with identified locations in Wetzel, Braxton, and Fayette counties of West Virginia.

The pipeline will be governed by the United States Natural Gas Act, which requires a Certificate of Convenience and Necessity (Certificate) from the FERC. Mountain Valley received this Certificate on October 13, 2017 and construction activities began in early 2018. With an estimated 20 linear miles of pipe remaining, MVP’s total project work is nearly 94% complete, which includes 55.8% of the right-of-way fully restored – the details of which are shown on the adjacent map.

As significant interest owner and operator of the proposed pipeline, interconnect links will redirect users to the EQM Midstream Partners, LP Customer Portal.